Bald Ridge Marina Road Pump Station

The Bald Ridge Marina Road Pump Station, Gravity Sewer and Force Main project includes a 35-HP Duplex Submersible Pump Station, approximately 3,000 LF of 12-inch DIP Gravity Sewer, 1,350 LF of 10-inch DIP Gravity Sewer, 1,100 LF of 8-inch DIP Gravity Sewer, 6,600 of 8-inch DIP Force Main, 400 LF of 24-inch steel casing, jack and bored under Georgia 400.  The project has been constructed under a very tight schedule and required several easements.