The Sawnee Creek Pump Station serves the drainage basin (6,445 acres) and pumps 3.9 MGD (2,706 gpm) per the City of Cumming's Sewer Master Plan.

The Sawnee Creek Pump Station includes three 133-HP Flygt Model CP-3300 submersible pumps.  GA Industries Checktronics Check Valves will be installed to reduce pump shutdown surges.  A 275 kW standby generator will provide continuous operation during power failures.  The 12-foot diameter wet well provides substantial storage for the ultimate flow requirement.